Key milestones have been achieved in Segment 5 of the ongoing road development works under the Malé North Side Boduthakurufaanu Magu Road Project Phase 1 in Malé, with water and wastewater main pipe installation works and settlement tank installation successfully completed. Current works include sewer upgrades, quaywall-side curbstone installation, cable junctions, and stormwater catchpits, all on track for completion within the week. Next week, sub-base preparation, ABC laying, and asphalt works are scheduled to commence. Meanwhile, sheet piling across Segments 2, 3, and 4 continues to progress, with 243 meters (47%) completed to date, reflecting steady advancement in the infrastructure upgrade programme in the Maldives.
Key milestones have now been achieved in Segment 5, with water and wastewater main pipe installation works successfully completed, along with the installation of settlement tanks.
— MTCC Plc (@MTCCPlc) April 22, 2026