Work continues to advance steadily on Segment 5 of the Malé North Side Boduthakurufaanu Magu Road Project (Phase 1), with preparatory activities for quay wall concreting now underway. This follows the successful completion of building-side curbstone installation and settlement tanks. In the coming days, works will expand to include stormwater catch pits, cable junction installations, and upgrades to MWSC sewer and water networks. Meanwhile, progress on Segment 4 remains strong, with sheet piling reaching 84 meters, marking another milestone in the project’s development.
Progress continues at a steady pace on Segment 5 of the Malé North Side Boduthakurufaanu Magu Road Project (Phase 1). Preparatory works for quaywall concreting are currently underway, following the successful completion of building-side curbstone installation and settlement… pic.twitter.com/E2jFs3kvgR